The Klickitat County Agriculturist, Goldendale, WA., October 5, 1907, page 16
WHAT THE NORTH BANK ROAD IS DOING
It is expected that the North Bank Road will be completed
as far as Lyle by October 15, and that passenger trains will be put on to
connect with the boat line at that place as soon as the rails are laid. This
is the opinion of W.A. Zimmerman, agent for the North Bank and regulator
line at The Dalles. Mr. Zimmerman said that tract laying has proceeded close
to The Dalles, and was being pushed with a great force. There are still some
rock cuts to be made the other side of Lyle, but that will not delay the
work, as the track will be laid around bad places on the old grade, and used
as a temporary track. Fourteen crews are now engaged in running construction
trains between Cliffs and Pasco, although no regular freight schedule is
yet maintained. The road is still being ballasted as far as the rails are
laid, and is ready for business.
Track laying will be started at Vancouver the first of
the month and the grade is finished as far as Cape Horn, so that trains will
be run out of Vancouver as fast as the tract is laid. The road will be a
double tracked at once as fast as the track is laid. The road will be double
tracked that once as far as the Cape Horn tunnel, and until a road is completed
between Lyle and the big tunnel, transfers between these points will be made
by boat. It is the intention of making their running time two hours between
the station opposite The Dalles and Portland, in which case the road will
get many passengers from the Oregon side. While the O.R. & R. is improving
its road a great deal, and will be able to reduce its running time, yet the
North Bank will have a much straighter track and will be able to make better
time, in the opinion of railroad men, as the road has been built with that
end in view from the start.
But whether the road is finished November 15 or May 1,
no one who has had an opportunity to make a close inspection of the engineering
problems which have been accomplished will accuse either contractors or engineers
of loafing on the job, and the completeness and thoroughness of the work
is the admiration of the initiated and the novice as well. In fact is probably
the only railroad that has been built in this country on which the grade
will be absolutely complete when a train schedule is put into operation over
it and which will allow a speed of 60 miles an hour from the start, if its
management sees fit to run trains at that rate, and they say they will.
Running through Lyle is a two mile stretch that will
require considerable work in addition to a bridge which is being built over
the Klickitat River. A mile below this is one of the most expensive bits
of construction on the line. Here in a distance of a mile are four tunnels.
They have cost the new road $300,000, exclusive of the track laying, and
are not finished yet, although trains could be running through three of them
if necessary. At the west end of the forth a steam scraper is at work removing
thousands of cubic yards of sand that for many months baffled the engineers
and resulted in the death of one man and seriously injured four more. The
configuration of the ground is of such a nature that steam shovels cannot
be used, owing to the fact that the sand crowds down on the shovel and chokes
it and is now being removed by scraping off the top and going down to grade
gradually. Workmen are at present concreting this series of tunnels.
All tunnels on the new road will be concreted with the
exception of the one at Cape Horn, which is over 4000 feet long - the longest
on the road, the rock in it being of a nature that is considered safe without
the use of concrete. The tunnels are 16 feet wide by 24 feet high and when
finished will be faced with substantial portals. At the east approach to
this series of terminals is the longest trestle on the road - one hundred
feet over a mile - and said by contractors to have been built to stand a
speed strain of 60 miles an hour.
Apposite Memaloose Island is to be found an uncompleted
section of grade through which runs a culvert 12 feet in diameter. It is
the outlet for a creek which is expected to use for fluming lumber down from
a timber belt back from the river. Like all the undercrossings and culverts
along the new road, it is built of solid concrete and is one of the permit
pieces of work, not usually put in on the first construction of a
railroad.
Directly below this, considerable rock work remains to
be completed, one section of which is still to be blasted out, which will
require several months of work. It is located near what will be one of the
most spectacular points on the road, huge rocks rearing themselves alongside
the grade toward the river, affording a sight similar to the Pillars of Hercules
and consisting of four instead of two great masses of stone, apparently up-ended.
Below this is a long fill, the piles for which is evident that there is still
much work.
Approaching Bingen, the grade is completed. The mountain
of rock opposite Mosier, which was blown into the river last winter, has
received additional attention since, having been cut away many feet back
from the grade to prevent ice formations from dropping on it, and presents
the appearance of a huge wall of hundreds of feet in height, which has been
gone over by a stone cutter with a gigantic cutting tool. Along there is
said by the chief engineer is to be the best finished piece of granite on
the whole line of the new road.
Below this the grade is completed to the White Salmon
river. The bridge of the former remains, however it to be built. Work was
commenced on it early last spring, but high water in the Columbia flooded
the excavations for the abutments, and it has not lowered sufficiently to
allow operations to be resumed.
From Underwood to Drano, a distance of seven miles, work
is being pushed rapidly, but there are a number of uncompleted pieces of
grade in addition to work on the four tunnels. The tunnels are bored, and
are now being concreted, and all are in about the same stage of completion
as those situated on the upper end of the division near Lyle. At Drano a
trestle nearly a mile in length is yet to be finished. A bridge over the
Little White Salmon river must also would be built on this section. Seven
miles above Stevenson the bridge over Wind river is also one of the pieces
of construction that remains unfinished. It is not believed by contractors
that this long stretch of uncompleted grade from Lyle to Cape Horn can be
finished sufficiently to allow trains to be run over it by November first.
The unusual width of the grade of the new road has been
the cause of much speculation by railroad men and others who have wondered
why so much expense was being entailed for a single track road when a narrower
road would have answered the purpose. This is now explained by the fact that
it was the original intention to double track the road except on bridges
and in tunnels. This order was afterward modified to double-track 20 miles
out of Kennewick and from Vancouver to the west end of the Cape Horn tunnel
which will be done as soon as the road is in operation. The great expense
at which the railroad has been built from Kennewick to Portland estimated
at $10,000,000, is said to be justified when it is taken into consideration
that the Portland & Seattle will virtually be the outlet to Portland
of both the Northern Pacific and Great Northern for all through freight in
addition to picking up a big local business from the grain country of eastern
Washington and points along the line.
[HOME]
© Jeffrey L. Elmer